AUTONOMOUS DECISION MAKING IN VERY LONG TRAVERSES (ADE)

You are here: Home » Milestones

Milestones

ADE will last 24 months starting from March 1st, 2019.

The project milestones are depicted in table here below.

Mile-stone
No.
MilestoneAcronym Milestone Name Related Work Package(s) EstimatedDate Location

Means of Verification

MS-1 KOM Kick-Off Meeting WP  0000 T0 GMV Project started
MS-2 PM1 Progress Meeting 1 WP  1000 T0+1.5m Telco MoM with progress status
MS-3 SRR System Requirements review WP  1000 TO+3m TAS-I Delivered SRR Doc.
MS-4 PM2 Progress Meeting 2 WP  2000 T0+5m Telco MoM with progress status
MS-5 PM3 Progress Meeting 3 WP 2000 T0+7m Telco MoM with progress status
MS-6 PDR Preliminary design review WP  2000 TO+9m GMV Preliminary Design delivered.
MS-7 PM4 Progress Meeting 4 WP  3000 T0+11m Telco MoM with progress status
MS-8 PM5 Progress Meeting 5 WP 3000 T0+13m Telco MoM with progress status
MS-9 CDR Critical Design Review WP  3000 T0+15m GMV CDR held. Detailed Design and identified Prototypes delivered.
MS-10 PM6 Progress Meeting 6 WP  4000 T0+17.5m Telco MoM with progress status
MS-11 PM7 Progress Meeting 7 WP 4000 T0+20m Telco MoM with progress status
MS-12 TRR Test Readiness Review WP  4000 T0+22m GMV TRR held. ERGO system level test successful. Ready for field test.
MS-13 PM8 Progress Meeting 8 WP  5000 T0+23m Telco MoM with progress status
MS-11 FA/FP Final Acceptance/ Final Presentation WP  5000 T0+24m PSA Test results validated. Final report delivered.

List of milestones.